NASA's inspector general raises questions with cost management of Orion spacecraft

NASA's Office of Inspector General (OIG) released a report yesterday (July 16) scrutinizing the management of

توسط MRAMINS در 28 تیر 1399

NASA's Office of Inspector General (OIG) released a report yesterday (July 16) scrutinizing the management of the agency's Orion Multi-Purpose Crew Vehicle Program.

Among the findings, the OIG determined that Orion — the next-gen capsule that will carry NASA astronauts to the moon and other deep-space destinations — has continued to experience cost increases and schedule delays. 

Since the cost and schedule baseline was set in 2015, the program has experienced over $900 million in cost growth through 2019, a figure expected to rise to at least $1.4 billion through 2023, the report concluded.

Related: The Orion space capsule: NASA's next spaceship (photos)

Since 2006, NASA has been developing Orion to transport astronauts beyond low-Earth orbit, with aerospace company Lockheed Martin as the capsule's prime contractor. The near-term focus for Orion is the moon; NASA aims to land two astronauts near the lunar south pole in 2024, as part of its ambitious Artemis program

Orion has flown three test flights to date, including one to Earth orbit, but none have had astronauts on board. The huge rocket that will launch Orion on its Artemis missions, the Space Launch System, has yet to fly at all. Orion and SLS are scheduled to fly together for the first time in late 2021, on a test mission that will send an uncrewed Orion around the moon.

The OIG report also found that NASA's exclusion of more than $17 billion in Orion-related costs has hindered the overall transparency of the vehicle's complete costs. Both federal law and NASA policy call for a life-cycle cost estimate for all major science and space programs costing more than $250 million, and for the "Agency Baseline Commitment" to be based on all formulation and development costs.

"The Orion Program received approval from the NASA associate administrator to deviate from those requirements, resulting in exclusion of $17.5 billion in Orion-related costs from fiscal year (FY) 2006 to FY 2030 due to the agency’s tailored approach to program management and cost reporting," the report states. 

"Although these exclusions have been approved, the tailoring of these cost-reporting requirements significantly limits visibility into the total amount spent on development and production efforts," it adds.

You can read the full OIG report here.

Leonard David is the author of "Moon Rush: The New Space Race," which was published by National Geographic in May 2019. A longtime writer for Space.com, David has been reporting on the space industry for more than five decades. Follow us on Twitter @Spacedotcom or Facebook. This version of the story published on Space.com.